Meadow Close Flats
Meadow Close is a residential development on Ross Road in Hereford, built with Unity precast reinforced concrete columns and a pitched roof carried on timber trussed rafters at about 900mm centres. The tiled covering, the battens beneath it, the fascias and the rainwater goods had all reached the end of their life.
Connexus Homes appointed Central as principal contractor, with Sustainable Group administering the contract. What was priced as a strip and re-tile became something larger once the covering came off: the trusses were sound, but there was no bracing in the roof at all. Around 860m² of roof over 24 occupied flats was rebuilt from the structure up, in three months, with residents in their homes throughout.
- Client
- Sustainable Building Services Ltd
- Timescale
- 3 months
- Date
- April 2025
- Project Manager
- David Alden , Herefordshire
- Project Location
- Hereford
After
Before
task
The pitched roof at Meadow Close had an ageing tiled covering on battens, with fascias, rainwater goods and associated details of the same age. It needed replacing. What made the job more than a re-tile was underneath.
Before the main works the covering was opened up and the structure inspected from both roof and attic level. The timber trusses themselves were in good condition, with no significant rot or decay. But they were widely spaced, and the original construction had no diagonal or longitudinal bracing within the roof structure at all. Putting a new covering straight back on was not an option; the structural arrangement had to be addressed first, and addressed correctly, because the new build-up would conceal it.
The roof also carried a long list of things to work around — chimney stacks, gas flues, soil and vent pipes, bathroom extract ventilation, fascias, rainwater goods and party-wall details — and all 24 flats stayed occupied for the duration.
approach
Three specialists were brought in before anything came off the roof. Curtins Consulting carried out a structural survey that established the construction and condition of the trussed roof, identified the missing bracing and set the strengthening solution. Central commissioned Environmental Management Solutions to carry out a refurbishment asbestos survey ahead of intrusive work; the soffit and fascia areas in scope were fully accessed and no asbestos-containing materials were found. Marley then produced the project-specific NBS specification following a visual inspection.
The work was sequenced so the building spent as little time open as possible — strip, strengthen, membrane and battens, tile, then final detailing — with each area returned to a weather-resistant condition as it went.
Because the flats were occupied, the site arrangements were built around keeping residents, visitors and passers-by away from work at height. 2m Heras fencing secured the perimeter and Haki stair access controlled the route to roof level, with the scaffold, loading and compound areas segregated. Exclusion zones, signage and cordons sat beneath active work, and materials were secured at roof level against wind. Gas flues running through the working areas were temporarily disconnected for the duration of the works, then reconnected and tested by a Gas Safe registered engineer. Day to day, the job ran on project-specific RAMS, daily Safe Start briefings and Safe Finish checks.
solution
The existing tiles, battens, redundant materials and rainwater goods were stripped and taken away, and the chimney stacks reduced below the level of the new roofing, capped, vented and made safe.
New treated timber rafters were installed to the roof and mansard where the structural survey called for them, with strengthening gussets to the roof and mansard rafters and joint arrangements between them, plus new 100 x 25mm timber supports for the lead top off the mansard. New fire and smoke barriers were installed at the heads of the party walls.
Above the structure, a Marley Universal vapour-permeable underlay went on with counter battens and new graded treated battens, and thermal performance was improved with 300mm of insulation at the eaves. The finished covering is Marley Ludlow Major concrete interlocking tiles in Antique Brown, with proprietary Marley dry-fix ridge, verge, valley and ventilation components. The roofline was renewed alongside it: new fascias and rainwater goods, lead slates to the copper overflow pipes, eight new or extended soil pipes, and 18 new tile vents with adaptors serving the bathroom extract fans.
The result is a complete roof envelope rather than a new covering — structure, insulation, fire compartmentation, ventilation, drainage and finish — delivered in three months under a 15-year guarantee, with the existing trusses retained and strengthened rather than replaced.