Conway Primary School
Conway Primary School sits on Conway Road in Sparkbrook, Birmingham, hemmed in by a residential street on one side and its own playground and car park on the others. Its roof is anything but simple: steep plain-tiled gables, valleys running between them, dormers, glazed roof lanterns and a run of flat-roofed blocks, all gathered around a tall central tower.
Surveys found ageing felt, ponding from too little drainage, and weathered, slipping tiles. Central was appointed principal contractor by Create Partnership, with Make Consulting as designer, and refurbished all 2,835m² in two phases while the school stayed open.
- Client
- Make Consulting
- Timescale
- 10 months
- Date
- May 2026
- Project Manager
- Jon Price , Birmingham
- Project Location
- Birmingham
After
Before
task
The school’s roofs had reached the end of their working life. The felt on the flat roofs was ageing, and on the corridor roof water stood after rain because there was not enough drainage. Across the pitched roofs the plain tiles were weathered and slipping, moss had taken hold in the valleys, and the flashings were defective.
The shape of the building made all of it harder. Valleys meet between steep gables, dormers sit in the slopes, and several chimneys and the central tower break through the roofline. Each junction needed its own detail.
Then there was the site. It is very restricted, with a residential street of parked cars along one side and the playground and car park on the others, leaving little room for scaffold, materials or a compound. The school stayed open throughout, with classrooms directly beneath the slopes being stripped.
approach
The work was split into two phases, each its own contract. Phase 1 took on three roofs over 8 months, including six valleys and three small flat roofs. Phase 2 followed in 2025 and covered the remaining tiled roofs, five flat roofs and the rooflights over 10 months.
With so little space, everything was planned around access. Compounds and roof access points were fenced off with Heras panels. The main scaffold, erected to TG20:21 guidance, carried a double protection lift with polythene between the boards where it met the pavement. Materials went up by telehandler to scaffold loading bays in small bundles, with a banksman guiding each lift, and tools and spoil came off the roof at the end of every day.
Inside, debris and safety netting went up under the ceilings to catch any plaster disturbed as the slopes above the classrooms were stripped. Work ran on weekdays between 8am and 5pm, with anything outside those hours agreed in advance with the client’s contract administrator, and every visitor was inducted and escorted on site.
On the Phase 1 valleys and small flat roofs, Alumasc’s Caltech QC system is cold-applied, so no flame was needed. Where torch-on felt went down in Phase 2, each roof ran under a hot works permit with a fire watch before the permit was closed.
solution
On the pitched roofs, the old tiles, battens and underlay came off from the top down in manageable sections. The roof timbers were inspected and repaired where needed, then a new breathable membrane and battens went on and the slopes were re-tiled in Marley Acme Single Camber plain tiles. New lead flashings went in at the chimneys, dormers and abutments, continuous ventilation from Manthorpe and Permavent keeps air moving through the roof, and Knauf insulation went in. On the Phase 1 roofs the ridges are dry-fixed with Marley’s Universal RidgeFast system.
In Phase 1, six valleys between the pitched roofs and three small flat roofs were lined in Alumasc Caltech QC, a PMMA liquid membrane laid with a reinforcing fleece so it runs as one continuous layer around every upstand and junction. That work carries a 20-year Alumasc system warranty.
In Phase 2, five flat roofs were overlaid rather than stripped. Each was cleaned and primed, then given a new vapour control layer, insulation, underlay and mineral-faced cap sheet in a Hera felt system. The rooflights were replaced as part of the same phase.
Across both phases, all 2,835m² of roof has been renewed, and the school kept teaching beneath it the whole time. The building looks as it should: red plain tiles, steep gables and the tower at its centre.